SCHEDULE

KPU intends to use FERC’s Integrated Licensing Process (ILP) for this relicensing. The ILP is FERC’s default process and provides a predictable, efficient, and timely licensing process with early identification and resolution of necessary studies. The table below presents a detailed process plan and schedule with timeframes and deadlines for the balance of the relicensing process. This schedule might reflect deadlines that fall on weekends (Saturday or Sunday) or federal holidays. All deadlines on weekends or federal holidays will default to the following Monday in accordance with FERC regulations.

Some steps in the relicensing process will only be conducted if needed. These are greyed out for easy reference. These deadlines are based on a NOI and PAD filing date of March 31, 2025.

Process Plan and Schedule

Responsible Party

Milestone

Timeframe

Deadline

18 CFR §

KPU

File NOI and PAD

5 to 5.5 years before license expiration

3/31/2025

5.5 and 5.6

FERC

Initiate Tribal Consultation

Within 30 days of NOI/PAD filing

4/30/2025

5.7

FERC

Issue Notice of NOI/PAD and Scoping Document 1 (SD1)

Within 60 days of NOI/PAD filing

5/30/2025

5.8(a)

FERC

Hold Public Scoping Meeting(s)

Within 30 days of NOI/PAD notice and SD1 issuance

6/29/2025

5.8(b)(3)(viii)

KPU

Hold Site Visit

Concurrent with FERC’s Public Scoping Meeting(s)

6/29/2025

5.8(b)(3)(viii)

FERC, KPU, and LPs

File Comments on PAD/SD1 and Study Requests

Within 60 days of NOI/PAD notice and SD1 issuance

7/29/2025

5.9

FERC

Issue SD2 (if needed)

Within 45 days of SD1 comment deadline

9/12/2025

5.10

KPU

File Proposed Study Plan (PSP)

Within 45 days of PAD comment deadline

9/12/2025

5.11(a)

KPU

Hold Initial PSP Meeting

Within 30 days of PSP filing

10/12/2025

5.11(e)

KPU

Hold Additional PSP Meeting(s) (if needed)

Within 90 days of PSP filing

12/11/2025

5.11(e)

FERC and LPs

File Comments on PSP

Within 90 days of PSP filing

12/11/2025

5.12

KPU

File Revised Study Plan (RSP)

Within 30 days of PSP comment deadline

1/10/2026

5.13(a)

LPs

File Comments on RSP

Within 15 days of RSP filing

1/25/2026

5.13(b)

FERC

Issue Study Plan Determination (SPD)

Within 30 days of RSP filing

2/9/2026

5.13(c)

Mandatory Conditioning Authorities

File Notice of Study Dispute (if warranted)

Within 20 days of SPD issuance

3/1/2026

5.14(a)

FERC

Convene Dispute Resolution Panel(s)

Within 20 days of Notice(s) of Study Dispute

3/21/2026

5.14(d)

KPU

File Comments on Study Dispute(s)

Within 25 days of Notice(s) of Study Dispute

3/26/2026

5.14(i)

FERC and Agency Designee

Select Third Panel Member (for each study dispute)

Within 15 days of Convening the Dispute Resolution Panel(s)

4/5/2026

5.14(d)(3)

Dispute Resolution Panel(s)

Hold Technical Conference

Prior to Engaging in Deliberative Meetings

TBD

5.14(j)

Dispute Resolution Panel(s)

Deliver Findings and Recommendations

Within 50 days of Notice(s) of Study Dispute

4/20/2026

5.14(k)

FERC

Issue Study Dispute Determination

Within 70 days of Notice(s) of Study Dispute

5/10/2026

5.14(l)

KPU

Conduct First Study Season

After SPD issuance

2026

5.15(a)

KPU

File Initial Study Report (ISR)

Within 1 year of SPD issuance

2/9/2027

5.15(c)(1)

KPU

Hold ISR Meeting

Within 15 days of ISR filing

2/24/2027

5.15(c)(2)

KPU

File ISR Meeting Summary

Within 15 days of ISR Meeting

3/11/2027

5.15(c)(3)

FERC and LPs

File Disagreements/ Requests to Amend the Study Plan (if warranted)

Within 30 days of ISR Meeting Summary

4/10/2027

5.15(c)(4)

KPU

File Responses to Disagreements/ Amendment Requests

Within 30 days of ISR Meeting Summary Disagreement(s)

5/10/2027

5.15(c)(5)

FERC

Issue Determination on Disagreements/ Amendments

Within 30 days of Responses

6/9/2027

5.15(c)(6)

KPU

Conduct Second Study Season (if needed)

After First Study Season

2027

5.15(a)

KPU

File Updated Study Report (USR)

Within 2 years of SPD issuance

2/9/2028

5.15(f)

KPU

Hold USR Meeting

Within 15 days of USR filing

2/24/2028

5.15(f)

KPU

File USR Meeting Summary

Within 15 days of USR Meeting

3/10/2028

5.15(f)

FERC and LPs

File Disagreements/ Request to Amend the Study Plan (if warranted)

Within 30 days of ISR Meeting Summary filing

4/9/2028

5.15(f)

KPU

File Responses to Disagreements/ Amendment Requests

Within 30 days of Meeting Summary Disagreement(s) filing

5/9/2028

5.15(f)

FERC

Issue Determination on Disagreements/ Amendments

Within 30 days of Response filing

6/8/2028

5.15(f)

KPU

File Draft License Application (DLA)

No later than 150 days before Final License Application (FLA) deadline

3/3/2028

5.16(a)

FERC and LPs

File Comments on DLA

Within 90 days of DLA filing

6/1/2028

5.16(e)

KPU

File FLA

No later than 2 years before license expiration

7/31/2028

5.17

FERC

Issue New License

Before the current license expires

7/31/2030